The City of Renton has provided an update on the Rainier Avenue South (Phase 4) project, confirming that construction is nearing its final stages despite delays caused by a recent atmospheric river event. Prolonged wet weather over the past few weeks slowed progress; however, crews continued working whenever conditions allowed.
According to city officials, remaining work will pause during the holiday season, with construction scheduled to resume on January 5.
Work Completed / In Progress:
-
Crews have made steady progress despite challenging weather conditions.
Final Tasks to Be Completed After January 5:
-
Grading and paving of driveways
-
Irrigation and landscaping
-
Striping
-
Median installation
Holiday Work Pause:
-
No construction work: December 22 to January 2
-
Crews return: January 5
Traffic Advisory:
-
Intermittent road closures for striping will occur on side streets through Friday, December 19, including:
-
S. 2nd St.
-
Tobin St.
-
Victoria St.
-
Hayes Pl.
-
Nelson Pl. NW
-
NW 3rd Pl.
-
-
All work is weather dependent.
Residents are encouraged to stay informed by visiting the city’s official project page at rentonwa.gov/rainier4 for the latest updates.